▲ Waiting for Kavya, the design head
Every project passes through her. A design takes her about 8 working days, so this queue is 24 days long.
#ProjectWaitingContractBill at approval
1Kumar and Shetty, Chartered AccountantsOffice, 2,400 sq ft28 days₹21,40,000₹6,42,000
2Dr Ramaswamy VenkatachalapathyVilla, Whitefield, 4 BHK25 days₹32,50,000₹9,75,000
3Sobha Dream Acres, A-7022 BHK kitchen and wardrobes17 days₹7,20,000₹2,16,000
Held behind the design desk₹61,10,000₹18,33,000
Of a project's 74 days on average, 26 are spent waiting for design. Anything that takes work off Kavya's desk (site measurements, client calls, drawings a junior can do) brings bills forward.
Cash cycle
Material is paid for before the client pays the stage bill.
Client pays a stage bill after31 days
Suppliers give7 days
Paid for material, not yet billed₹14,20,000
Bills raised, not yet paid₹9,86,000
This year
Projects handed over22
Billed since April₹1,86,40,000